Meetings and Reports

Representatives of the Contractor, approved by the Engineer, shall attend monthly progress meetings on Site or at the offices of the Employer. In addition, approved representatives of the Contractor shall attend further meetings in cases of emergencies or for other reasons when called upon by the Employer.

The Contractor shall submit to the Engineer Daily, Bi-week, Monthly and Quarterly Reports on his progress in the performance of the Contract. The Monthly and Quarterly Reports shall include a copy of the approved programme with the current progress for each activity shown. The Contractor shall provide Monthly and Quarterly Video records of the Works executed during this period.