Not less than 14 days before commencing any portion of the Works, the Contractor shall if ordered; submit to the Engineer for his approval complete drawings and calculations for all Temporary Works which the Contractor may propose for the construction of that part of the Works.
Notwithstanding approval by the Engineer of any design for the Temporary Works, the Contractor shall be entirely responsible for their efficiency, security and maintenance and for all obligations and risks in regard to such Temporary Works specified or implied in the Contract.